The DeKalb County Engineer reminds residents, “The Tollway has announced that the start of the Somonauk Road Bridge Overpass project is being postponed for a week until April 9, 2018, pending review of the Contractor’s Structural Assessment Report”.
This work will be done under traffic (one lane closed-one lane open) with temporary traffic signals for the Somonauk Road Bridge. Keslinger Road Bridge will be closed to all traffic. Repairs will include deck and substructure repairs with concrete overlay and guardrail replacement if impacted by bridge work for Somonauk Road Bridge. Keslinger Road Bridge will have the deck replaced with vault removal and substructure repairs along with guardrail replacement. Work is scheduled to be completed by mid-July 2018. Any questions or concerns can be addressed to the County Engineer at 815-756-9513.
Click Here To Submit A News Tip Or Story