Construction is heading to the north side of Locust Street starting on Friday, October 8. This means traffic control will change and vehicles will now be able to enter from North First and head eastbound on Locust.
On the south side of Locust, bricks will begin to be installed on Friday. Brick installation and other sidewalk work will continue through next week. The south side will be open now to eastbound traffic, but there will be almost no parking at this time on Locust due to the work on the sidewalk and on the north side.
The lights from 1st to 2nd will not be lit until the work on the north side is complete. Utility poles will remain until next spring. Utility companies will arrange for the cross over connections with businesses and residents over the winter. Sections of sidewalk have not been poured adjacent to the existing light poles. Those sections will be filled with stone for the winter and paved once poles are removed in the spring.
On the north side of Locust, demolition will begin on Friday following the traffic control change over. Work will begin at the west end at 1st and Locust and move east. All sidewalk and roadway pavement will be removed at once. The contractor will continue working on Saturdays. At times roads and driveways will be blocked while they are removing pavement, but this should only be spot closures from time to time.
If there are any questions please contact Joel Maur, City Engineer at 815-748-2000 or Jennifer Groce at Re:New DeKalb at 815-748-7788.